Setting an Audit To Planned

  • Updated

Once your audit is in draft and you have a date in mind for when the audit will be carried out you can set your audit to Planned.

  1. Go to Audits > Audits.
  2. Select the Draft Audit that you would like to set to Planned.
  3. From the Status dropdown select Set to Planned.
  4. Select the Planned Date.
  5. Input User details and password.
  6. Include any relevant Remarks.
  7. Click Save.

 

 

  Relevant for: Administrators / Managers / Regular Users

Was this article helpful?

0 out of 0 found this helpful